Board of TrusteesOctober 7, 2026 Meeting recap

Oscoda budget session: sewer and water budgets reviewed, tap fees and postage flagged

Trustees reviewed the draft 2027 sewer and water funds line by line on Oct. 7, raising questions about tap fees that may not cover costs, postage tracking and a missing water main under US-23; no budget action was taken.

Why it matters to you

The sewer and water funds pay for the systems that serve township utility customers, and officials said a rate study projects about 3% annual rate increases, with another rate evaluation expected in mid-2027. Tap fees for new connections may also be revisited.

What they decided

  • Approved Meeting chair selected With the supervisor absent, the board chose Treasurer Jaimie McGuire to chair the budget work session. Vote: 4-0
  • Discussed Sewer budget reviewed (Fund 590) The board reviewed the draft 2027 sewer budget, including $500,000 for a new CWSRF project and questions about postage, tap fees and PFAS plant electricity. No action was taken. $500,000.00
  • Discussed Water budget reviewed (Fund 591) The board reviewed the draft 2027 water budget, including $800,000 to finish a $3 million EPA grant and questions about the F&B contract and hydrant billing. No action was taken. $800,000.00

The story

The Oscoda Township Board of Trustees spent about an hour on Oct. 7 reviewing the draft 2027 budgets for the sewer fund (Fund 590) and the water fund (Fund 591) at a budget work session at the Robert J. Parks Library. The session was for discussion only; according to the minutes, the only vote was to select Treasurer Jaimie McGuire to chair the meeting, 4-0. Trustee Regina Fortner arrived at 6:10 p.m., and Nicole Tregear was absent. Rick Freeman presented both funds, according to the agenda. No one spoke during public comment.

Sewer fund

Officials said about $150,000 from the current Clean Water State Revolving Fund (CWSRF, a state low-interest loan program) sewer project is carrying over into 2027 because of delays by Consumers Energy in getting power poles and an FAA permit. The draft also includes $500,000 for a new 2027 CWSRF project, mostly for design, bond attorney and equipment costs that can be reimbursed; officials said most construction would come in 2028.

Officials said a Baker Tilly rate study projects roughly 3% annual increases, and another rate evaluation will be done when the new loan project is set up, around mid-2027. Rates will be set later with the fee schedule. Officials said they believed sewer and water tap fees, charged for new connections, had not been adjusted since about 2010 or 2011, and said the fees may not cover the cost of the work; that is expected to be discussed at fee schedule time.

Other sewer items raised: - Postage for water bills and notices has been charged to the supplies line because the new chart of accounts has no postage line; staff will propose either raising the supplies budget or adding a postage line. - It was suggested that the township track electricity for the new PFAS treatment facility separately. Officials said it will be metered separately and that utility costs are not reimbursed. - Trustee Mark Wygant asked whether the vehicle insurance budget allowed for increases and why loan interest expense was rising. Officials said the township now insures only two vehicles for the department, a Vactor truck and a crane truck, and that interest is rising as early principal forgiveness on the loan ends; staff said they would verify both. - A board member asked that a revenue line be relabeled "ready to serve" so it is clearer.

Water fund

The draft water budget includes $800,000 to finish out a $3 million EPA grant, which officials said covers 100% of eligible costs up to that amount. Officials said roads are in worse condition than expected and more paving is anticipated. They also said a water main under US-23 between East and West River Road, shown on MDOT as-built plans from about 2012, was never installed, forcing a costlier bore under the highway as a change order; MDOT is looking into it.

According to figures given at the meeting, crews checking services in the downtown system found more than 30 of 40 services leaking. The township's contract with F&B for system operations is about $853,000, with six staff dedicated to Oscoda and a $20,000 chemical allowance. A board member said the contract is among the largest controllable costs and asked for staffing information.

Board members also asked how metered hydrant water use is billed; officials said the question is being investigated. The capital improvement plan lists hydrant replacements outside the former Wurtsmith base, after a 2027 drinking water loan application was not funded, and a Cedar Lake Road water main project shown for 2028.

Schedule

The general fund and remaining budgets are set for an Oct. 28 work session. Board members discussed adding a draft budget review session, possibly Nov. 10, ahead of a public hearing and adoption at the December board meeting. Officials noted the hearing notice would need to run in the newspaper around Dec. 2. Wygant said he would prefer the Oct. 28 session be a draft budget review; a board member noted changes in board seats and contract negotiations ahead.

This story was written by AI from the official records listed below, including the meeting minutes and/or recording. It may contain mistakes, so check the source documents before relying on it. Report an error. Last updated November 25, 2026.

TranscriptWatch on Zoom ↗

Automatic transcript from Zoom · 1:10:46 · may contain errors
  1. 0:00:06That is the last step.
  2. 0:00:08Please stand for the Pledge of Allegiance.
  3. 0:00:11I pledge allegiance to the United States of America, and to the Republic for which it stands, one nation, under God, indivisible, with liberty and justice for all.
  4. 0:00:25Roll call is next. Mr. Cummings? Here. Ms. McGuire? Here. Mr. Weigant? Here. Ms. Fortner?
  5. 0:00:33Oh, maybe I should talk again. Let's take your… Mr. Gear.
  6. 0:00:39So we do have a quorum. I do know we're expecting Ms. Mortner at some point, but I have not heard from Mr. Gear, so I will motion that we select who wants it, who wants to be the chair. I would actually… will you chair, Jamie? Because…
  7. 0:00:52You are a quick meeting lady. I'm going to motion that we select Ms. Jamie McGuire as our chair for the Soscoda Township Board for Session. I'm tired. I'll take it.
  8. 0:01:02All right. Motion is there support all support.
  9. 0:01:06Back in, mr. Wygant? Yes. Mr. Cummings?
  10. 0:01:12Yes. Ms. McGuire? Yes. Ms. Tate? Yes. Take it away, Jeannie. Okay. I'm still on GermanyCon, so, you know, agenda additions. We don't have enough people to have agenda additions, correct? So, move on to public comment.
  11. 0:01:30There is no public comment tonight.
  12. 0:01:32Moving on to business. Number one, we've got Sewer with Rick Freeman, and 8 is 1590. If I can, before we get started, I just wanted to, make sure the public knows that, in our zeal to get the correct information to the board, it was not out in appropriate time for you to be as well prepared as you normally are.
  13. 0:01:55So I just want to apologize.
  14. 0:01:57in advance.
  15. 0:02:00Thank you. It's appreciated.
  16. 0:02:03So… And now we can start.
  17. 0:02:12Okay.
  18. 0:02:16remark, Amanda.
  19. 0:02:19So, Rick, I've typically just been going down line by line, if they have any questions, we…
  20. 0:02:24adjustments they need to make, we make them on the fly, and then we fill them in later with, Caitlin?
  21. 0:02:31And I know the these are difficult.
  22. 0:02:38Budgets because of all the, projects and grants and loans that we… and bonds that we have going. So we do the best we can to explain.
  23. 0:02:52Should we start with the CWSRF,
  24. 0:02:562024, maybe explain why we only got 150. Yeah, so… so the CWSRF, project, that's the current one we have going on.
  25. 0:03:08Back up last year at this time, we were figuring that 2026 would be… we would wrap that up, but due to the consumer's energy issues with power out there, and getting their, permit from FAA, we've got a delay in getting the transformer poles up.
  26. 0:03:28So, that's why there's 150, thousand leaking over into 2027. There is a slight chance we might still be able to finish up in 2026, but, we thought it'd be best to hold off, because there'll be still probably some paperwork and…
  27. 0:03:46such with, Rose time as far as closing out the as-builts and all of that stuff. So, overall.
  28. 0:03:55that 2026 amended budget might get reduced down a little bit, because we're actually… it looks like we're coming in under budget, and that number was set back in 2026 as capturing the entire remaining amount of the C…
  29. 0:04:13Thank you. You called it the 2026 budget? The 6.8 million, that might… it might actually come down before the end of the calendar year. Budgeting it down to the road. Well…
  30. 0:04:29Yeah, yeah. It would be a budget amendment. It matters in terms of balancing the budget, that's it. Sure. I want to mention also, you noticed that, last…
  31. 0:04:40time last… we didn't have the original budget, and I know there's a couple questions going back to that, and you'll see that column in the sheets now.
  32. 0:04:49And I do appreciate going forward, going forward also.
  33. 0:04:54So… Continuing on down, we have budgeted, $500,000 for the new 2020… 2027 CWSRF for… for next year.
  34. 0:05:10the schedule for that project, we'll be working with EGLE to get all the paperwork in place, the plans in place.
  35. 0:05:17And would be probably putting that out for advertisement in the June, May, June timeframe, but then you gotta go through all the bond process, getting the contract awarded, so… Construction on that wouldn't be until this quarter next year.
  36. 0:05:34So, that $500,000 is a anticipated amount for equipment purchases at this time next year, also for rows, design fees.
  37. 0:05:46the bond attorneys and all of that, all that preliminary stuff, which we can get reimbursed for, and we will be submitting those in August, September, October next year, so that's why that's sitting at $500,000. So, majority of that project will be in 2028.
  38. 0:06:06I'm… Some of these other line items, I'm not 100% sure, charges for other services…
  39. 0:06:13So what is that? Is that Fnb.
  40. 0:06:15And…
  41. 0:06:19The charges for the… I was pretty sure… charge for the cliff services. I see sewer services. I'm gonna have to… I believe you're correct, however, I'm gonna have to refer back and ask, so I can give… I got so many numbers.
  42. 0:06:36Jumbling through my head, why…
  43. 0:06:38Because we just talked about it 3 minutes ago. So, on the second page, I see… Yeah, it's definitely… Oh.
  44. 0:06:47That's, 806.100, kind of, like, 3 quarters of the way down on the second page.
  45. 0:06:54Sorry, just on the second page, Adam. I know when I was looking at the water burden, charges for other services included user fees. Okay.
  46. 0:07:06Like, ready to serve this type of thing, but I don't think that applies on sewer, but it's… it's like that. Well, there is… there is a ready to serve on sewer, and that's what it does. And then there is sewer fees.
  47. 0:07:18Right, there's… So these are, these are… Sewer fees, ready to serve fees.
  48. 0:07:23Okay.
  49. 0:07:26But the FB, the right FB is down here. So we're counting charges for other services as ready to serve?
  50. 0:07:35And then the regular charges for sewer service, and the actual sewer fee of what goes through. And, we'll probably set those
  51. 0:07:45Amounts a little bit later, along that, ski, fee schedule, that same one that you used.
  52. 0:07:54I think it was Baker Tilly did a study… Right, for that annual increase? Right. Right. As it stands right now, they've projected out
  53. 0:08:03I think it's, like, a 3% increase annually. Now…
  54. 0:08:07when we go through the 2027 CWRSRF, getting that project all set up, there'll be another rate evaluation, so that if, you know, if we're all… we're still good at 3%, then we'll just continue with that. They will make a recommendation if it needs to be bumped up a little bit at that time.
  55. 0:08:26Okay. That would be mid… mid-year next… next year.
  56. 0:08:31Okay, June time.
  57. 0:08:33Bob.
  58. 0:08:35It's a small amount.
  59. 0:08:37But in regard to the sewer tap piece.
  60. 0:08:40We just… That's weird. We're mending back down, you know, new half, so…
  61. 0:08:48Just based on, kind of… New development, and not… We're not expecting a lot. … not projecting that much, right.
  62. 0:08:55But I would also say that there may be discussion about the fee itself, right, not being appropriate. However, we'll handle that at fee scheduling time. Not appropriate. It might not be high enough. Yeah.
  63. 0:09:10And I'm not sure exactly the timeframe, but I don't think the township has adjusted their fee schedule since…
  64. 0:09:172010, 2011, maybe? Something like that. I know it was… I know it was prior to my… my time. On the other hand, when we add a new tab.
  65. 0:09:26It's now going to be lifelong revenue.
  66. 0:09:29Right, but the… but the cost to physic… the… the material, the labor, and all that stuff has… has… Oh, we're not even breaking even. My understanding is that it's far more to actually do this. I thought we were saying we were trying to make a profit on… I don't think you're covering costs. Okay.
  67. 0:09:49Oh, we'll have to address that when we get to the eval. And a lot of the sewer taps are deeper.
  68. 0:09:55because of Servicing basements, and that, that was… Right.
  69. 0:09:59So, that exceeds F&B's capabilities, so a lot of times we have to kind of crack that open, like John Henry, whatever. Fair enough. The only other line item here on this, on this page is interest earnings.
  70. 0:10:13That's probably for you, Treasurer McGuire, but I'm assuming this is just because, I haven't posted the last two months.
  71. 0:10:21No, I know, but it's being the requested Budget is being budgeted down.
  72. 0:10:24Okay, that's just a safety thing. And either that, or I was wondering if we paid out funds to fund… to finish the project, so we're not going to have the same balance. I believe that's correct. Correct. Yes. Okay. At least talking Caleb, we're going to be paying out.
  73. 0:10:39Makes sense, yeah. So we won't be occurring as much on it.
  74. 0:10:48If you have to. Perfect.
  75. 0:10:50Thank you.
  76. 0:10:51But we have two new ones starting as well, so… Okay.
  77. 0:10:56Trustee Fortner arrived at the time again.
  78. 0:11:05That good?
  79. 0:11:07Thank you.
  80. 0:11:08Minimum interest in supplies.
  81. 0:11:14Air maintenance.
  82. 0:11:17Yes, so go on page 37, page 2.
  83. 0:11:21Yeah.
  84. 0:11:23So do that.
  85. 0:11:27Professional fees, we kept about the same.
  86. 0:11:31No.
  87. 0:11:32Can we identify that? Is that Plant Moran's portion, or is this engineering fees?
  88. 0:11:37This…
  89. 0:11:39I'm not sure about where Plant Moran would be, but it would be… it would be that your miscellaneous row expenses that aren't tied to… A project. An actual funded project.
  90. 0:11:52Is this where… my miscellaneous, my miscellaneous… And that engineering fees line. Yeah, okay. Yeah, sure. Oh, yeah. And then, any other projected, you know.
  91. 0:12:05Also, anticipated consultants that might have to be brought on as a sub-consultant, whatever, for the year.
  92. 0:12:11I'd like to go back to the supplies line item. Yep. I inputted an invoice today for $4,000, which bumps that over the amended budget, the original budget, and, yep, for supplies.
  93. 0:12:23Postage is being charged there. We discovered today that when the chart of accounts conversion happened, there's no separate line for postage. So we either need to up the supplies line, so I… and that'll be addressed in a transfer or an amendment for fourth quarter for this year.
  94. 0:12:38But for next year, we either need to up that number, or we need to create a separate line item for postage.
  95. 0:12:43Okay. And then put the appropriate amount of dollars in there. It's about $2,000 a month that they… well…
  96. 0:12:51I'm trying to think. I don't know what you… it's…
  97. 0:12:55how… it's, like, every two months they add, or every two months they ask for an in-border. Yeah, like, every quarter, right around there.
  98. 0:13:02I'd have to… I'll go back with an exact number, which we've spent so far on sources, and then we can go from there.
  99. 0:13:08the water… Water bills. This is for the letters. Yeah, water bills that go out, past due notices, any, any, like, notices that they send out. Yeah, they send the letter out over 3 months. We do a… they do a memo, and they request more postage, but we discovered today that, it's still going to the supplies line item. So, I'll get an exact number to you of how much we spent so far this year. We can address the amendment that we'll need, and then…
  100. 0:13:31For the next work session, we can have a number for that.
  101. 0:13:34But we need another… you… you think we need another line item?
  102. 0:13:39We either need to increase the supplies line item, or we need to add a line item for postage if we'd like to track it more exactly. Caitlin would probably be a good resource for that. If she thinks it's necessary, then you can have her create the line item, or we'll just up the supplies line item. It doesn't matter to me what we do, but…
  103. 0:14:00Okay.
  104. 0:14:17Audit fee, computer program fee.
  105. 0:14:21about the same… audit fee.
  106. 0:14:25about the same.
  107. 0:14:30tracking services.
  108. 0:14:32I don't think we have much… use there.
  109. 0:14:37We kept it about the same, just to have a little bit of a buffer, and then…
  110. 0:14:42the contracted services for, F&B, well, that would be the contracted number. Yeah, and that's the… they had a, escalating factor in their contract that they… so from 26 to 27, that's the difference. And the engineering fees is…
  111. 0:15:01basically, Rick's fees.
  112. 0:15:05Or water. That are allocated to sewer. I was gonna say… Sewer, sorry. This is where half of the bill goes. Yeah.
  113. 0:15:13I'm gonna ask a question.
  114. 0:15:16Bank fees. Did they all of a sudden quit charging us fees?
  115. 0:15:22We move that to… to, did we move that?
  116. 0:15:26Where do we move it to?
  117. 0:15:29here.
  118. 0:15:31Good question.
  119. 0:15:33Because it… No bank I know is gonna give us free stuff if they don't have to.
  120. 0:15:40It might be under another function of the 590. There's nothing in water, even.
  121. 0:15:4710, 17.
  122. 0:15:50like, maybe regulatory fees. I'm… I will have to check with Caitlin to see if…
  123. 0:15:55If, bank fees need to go back in there, then we'll put something back in there.
  124. 0:16:01I feel like that was one of those ones that got… Reallocated? Yes, thank you.
  125. 0:16:07BLT.
  126. 0:16:10If so, and we're going to carry that line item right there, we might just put reallocated next to the bank fees, so that we don't…
  127. 0:16:18keep asking the question. The bank fees are probably under 101 somewhere, like, in our general fund, because these enterprise funds are in our common checking account also, so it probably is coming out of that, the other number. Unallocated would probably be my guess.
  128. 0:16:33I can get you the answer. Yeah. That's probably why there was no activity for 26.
  129. 0:16:40Is there ever a way to get rid of it? Yeah, is there any way just to get rid of that so that we don't…
  130. 0:16:46The fees? No. Oh, there's activity in 24 and 25, so when we continue to do that, when we continue to do budget prep and they display, like, future years, then it'll drop off. There's a setting that will… it'll drop off. And I'll just say inactive and… All right.
  131. 0:17:04Then you just don't use it anymore.
  132. 0:17:08Sorry for interrupting. No. Any questions?
  133. 0:17:13Down to legal fees, we kept that the same.
  134. 0:17:22I'm gonna ask another question on that one. You can.
  135. 0:17:25Okay. Yeah. That's fine.
  136. 0:17:33With all the talk about how much we've been using our legal, Is that gonna be enough?
  137. 0:17:41who Well, and so far we've only used 1500.
  138. 0:17:46for 2026, and that's… Really? For the specific fund. Sewer. Oh, okay, this is just for sewer, okay. Thank you. that touches legal, like, the police have a legal, zoning has legal, we have an allocated general, so this would just be anything that was specifically charged to sewer department for legal services. Okay.
  139. 0:18:05Thank you.
  140. 0:18:09Okay.
  141. 0:18:12Oh.
  142. 0:18:14Yeah, too many spiders.
  143. 0:18:16Did another one come out?
  144. 0:18:18Fighter. Yeah. Second one.
  145. 0:18:21Thanks.
  146. 0:18:22Come on. Down there now. Well, so hopefully he's dead down there and not crawling up one of our legs.
  147. 0:18:28I hope not either.
  148. 0:18:31But, yeah, regulatory fees…
  149. 0:18:35That's the sewer, all the different variety of sewer permits and the stuff that we have to file with EGLE.
  150. 0:18:43combination rules.
  151. 0:18:46pursue all the Different permits. Different permits for the… in the paperwork that we had the RFID files for.
  152. 0:18:57keeping our system Good morning.
  153. 0:19:02Thank you.
  154. 0:19:03telephone, you know, I assume…
  155. 0:19:07We didn't talk about that. We did not. On the telephone, I was making an assumption, but I'm not sure if it's correct. One was that we are appropriately billing the correct telephone bills now to the right department, and then the other one was…
  156. 0:19:25didn't F&B, I don't know if that's gonna happen this next year.
  157. 0:19:30Or if it was already happening with their cellular services, or…
  158. 0:19:35I actually had that question, too. I was gonna bring it up. We have a meeting with Catherine tomorrow to discuss that.
  159. 0:19:42I think. As far as, yes, as far as that service. I think that was it, but nowhere that gets tracked. Again, this is half the bill. Half goes to sewer, half goes to water. Right. But assuming we allocated the same as last year and this year, I mean, it's a 40% increase in telephone services, which…
  160. 0:19:59So they have a landline that they get charged for, they have two iPads, they have an on-call phone.
  161. 0:20:05Yeah. Is that a difference from 2025? Or 2026? Right. The rates didn't go up very much either, so I would say, pending the results of your conversation, I don't know if there's something explained. That last conversation that…
  162. 0:20:19whichever board meeting that was. Right. That was the water side, too, as far as the… Oh, that wasn't necessarily… Yeah. This would be a question mark, then. Yeah. Look at the water line item, too, to see if it matches.
  163. 0:20:31But right now, when bills like that come, like, any… everything, like the printer bill, like, anything that pertains to the water and sewer departments gets split in half, and half gets allocated to sewer, half gets allocated to water.
  164. 0:20:42So that's how the phone is done, that's how…
  165. 0:20:45anything that goes there. I definitely don't want to muddy the water here, but it's an interesting way that our accountants have us doing that, seeing… because…
  166. 0:20:55There's a tremendous amount of more water service than there is sewer.
  167. 0:20:59I think some things… I think it's, like… I don't think it's half, I think it's, like… It's half and half. Is it half and half? Yep, that's how it's… I'm not looking to change the county. It's just interesting, because it's not really 100% accurate reflection of the cost.
  168. 0:21:15But whatever, you know.
  169. 0:21:19Printing and publishing, although, we kept… we…
  170. 0:21:25Marching down a little bit, because we don't have any activity.
  171. 0:21:282026. And part of that is, is all of our projects get… We're already done. Well, they're… well, they… but they get funded through the different grants. Grants repay us for the.
  172. 0:21:43advertising and all that type of stuff, so… Or if there's anything charged there, though, there'd still be activity this year. That means nothing's been reimbursed, because you can't reimburse a line item that we don't have to spend for. We should probably check that and see if any… if I need to reclass anything that was quoted incorrectly.
  173. 0:21:58You too.
  174. 0:22:00Do you have a question before we move off the page? Well, is this where envelopes and things would go? The printing? I would think so. I would think so, but that's not where they are. Maybe, but, like, the purchasing of supplies doesn't go to printing and publishing? No, if it's… if they're printing… if they're printing.
  175. 0:22:18Right, it's not postage, so, like, that's… the bulk of the supply line item right now is postage and printing and ordering of, like, their envelopes that they use to send, like, their… they have different notices, like, some people get a bunch of bills, and they put all of the bills in one envelope, and they have a lit, and it goes in a special envelope.
  176. 0:22:38We're talking, like, it's, like, $25 a box of envelopes, and they go through, like, 2 or 3 boxes a year. So, like, we're talking, like, under $100 worth of…
  177. 0:22:50Before we leave this page insurance vehicles. So
  178. 0:22:575. Where are you at? Okay, 5.200. Can we go back up to utilities?
  179. 0:23:03thought of this this afternoon after we had our meeting. Okay.
  180. 0:23:08Our new treatment facility out there is going to… have a electricity draw.
  181. 0:23:17So, I don't know if we should put a line item in there for the PFAS treatment facility.
  182. 0:23:23Okay. Do you separately track it? Well, it's gonna be… it's gonna be metered separately and all of that type of stuff through consumers. Okay. So, it might be worth…
  183. 0:23:38Oops. The only reason I say that is there's the water and DPW building here, and
  184. 0:23:43that, so it might be… I don't see anything… well, I guess it looks like utilities, water, sewer, there's nothing for the last few years, but then water, BPW building.
  185. 0:23:54There is activity, but it's the opposite for the electricity.
  186. 0:23:57So we should probably review all of that, actually.
  187. 0:24:03That's gonna be a 24-7 operation, so that's gonna… Are we getting reimbursed for any of that stuff, Rick, do you know? Not… not the… not the utility use, no.
  188. 0:24:15Obviously, all the equipment and stuff, yes, but… Not the actual utilities, okay.
  189. 0:24:20This is where we have that accumulation of expenses by the township over years, and…
  190. 0:24:27Right. That's what I was thinking, it might be a way to track it, so at least you've got a number in front of you. That you can use, that's exactly, yeah. I know we're skipping water department, or a lot of these things would get split. There's only one utility line item for electric.
  191. 0:24:47Adam, you said something individually.
  192. 0:24:50tracking that to… you could seek reimbursement in the future. Hopefully. Yeah. Absolutely. Which I know you're having difficulty with. Yeah, the residents along the township.
  193. 0:25:05Alright.
  194. 0:25:06Mark, you had a question on insurance vehicles. Yeah, towards the bottom. I see we're just carrying kind of over activity from 2026. We had budgeted quite a bit higher than that, but it's the exact same carryover.
  195. 0:25:19Are we just not…
  196. 0:25:21planning on insurance going up, or… I think we… we reduced some vehicles. Okay. What vehicles do we insure for the water department, do you know? The, Vector truck. The only would be the Vector truck and the crane truck.
  197. 0:25:37Yeah. The only two that are now Township. Every… all of the vehicles that F&B uses, they have now included that in their contract. Yeah. So it's… It seems a lot to be… Yeah, two massive…
  198. 0:25:49very expensive. For sure. I'm not saying it's wrong, it just… I would say maybe we check that, too. I think it's okay to over-budget a little bit anyways, because I know we've been in the past, so that we can move that money around if it's needed other places as well. We can look at…
  199. 0:26:02what an actual is, because that… that, 26 actual, I think.
  200. 0:26:07we may have paid before, because that was before we did it. That's exactly what I'm thinking, because I think we did have the FMV vehicle still on there when we paid in January. Yeah, because the new contract didn't take effect until May. I think a general rule of thumb would be on insurance renewals.
  201. 0:26:27Check the property listing right? So It'll list your views.
  202. 0:26:33So obviously, you know, like Al, for instance, out at
  203. 0:26:37Old Orchard should be able to review his insurance, and it shows, or whatever, or you with Al, or whatever. And then if, you know, a bunch of F-150s or whatever it is that F&B's driving around is showing up on that, check VINs and…
  204. 0:26:52make sure they're removed from the policy, or whatever. Yeah, you're… well… Or vehicles that are outside. Yeah, except they're not necessarily removed, because some got repurposed to DPW and the park, so… So the bill would be similar, but the cost would be allocated to… Right, allocated to folks, exactly.
  205. 0:27:13I do think we did drop a couple vehicles. I talked to Catherine today and she said she thought one truck went to DPW, one went to the parks.
  206. 0:27:21So, that checks out.
  207. 0:27:24Got it. No further questions on that page.
  208. 0:27:27And then that capital outlay… That 150 is the same budget, 150…
  209. 0:27:35improvement outlay, the 400,000, and what is it? They said that… You know, from the 500.
  210. 0:27:48From the CWSRF? Oh, it's capital.
  211. 0:27:54It's the same, though. It reflects both.
  212. 0:27:58That's on the last page. Yeah, the last page, yeah. Sorry.
  213. 0:28:03Last page for 590. I only have one question.
  214. 0:28:07Not sure how easy we can answer or not, but our actual interest expense
  215. 0:28:14is climbing again for CWSRF interest expense.
  216. 0:28:18I'm slightly confused.
  217. 0:28:21On how that's working since we've…
  218. 0:28:24paid off that bond this year. We won't be receiving the new bond until
  219. 0:28:30maybe sometime at the end of next year, why would our interest expense increase so dramatically? What one are you looking at, Mark? I'm sorry. Right in the middle, 590905993. 993, 000. 21.
  220. 0:28:47CWSRF, we haven't paid off that bond. No. The one below it, the CRF interest, the 215, 2015 one? The SRF. Yes, SRF. But I'm questioning the one… Oh, I'm sorry, not SRF, the WWTL bond one. There should be nothing there, and there is. Okay, but I'm questioning the one, too, above that, Jamie. 993- or .000, the actual CWSRF interest expense.
  221. 0:29:11He's still… we're still making bond payments on that.
  222. 0:29:15Okay, that's fine. Why is it increasing?
  223. 0:29:18As our balance is going down, why is our interest expense going up?
  224. 0:29:22I'd have to look at the bond, the sheet, but we got, like, a discount thing for the first couple years, and then the payments, like, we only paid a minimal portion the first couple years, if I remember correctly. You had principal forgiveness. Yeah. And that factors into a lower interest rate.
  225. 0:29:40But then it started… Right, now it's… now it's gone back to the regular principal and interest with the bigger portion, and working its way down. But I can… I can verify that. That's fine. I think you did a… you probably did a fourth quarter
  226. 0:29:57cheap from the state that redistributes all that. The bond payments, what is this? I did them in September or October, so I have the most current one. I'll send it to everybody.
  227. 0:30:10That's my only question on the rest of 5 90.
  228. 0:30:14Yes.
  229. 0:30:23of the internet.
  230. 0:30:28Is it 590, or even more questions?
  231. 0:30:35591.
  232. 0:30:37Okay.
  233. 0:30:42EPA… capital loan… capital improvement, loan forgiveness.
  234. 0:30:48We get Budgeted 800,000.
  235. 0:30:53Yeah, that's… so that's… so… so we have a $3 million grant. We had a… when that got all set up, a…
  236. 0:31:02Not sure, 20 or 25% local match to it.
  237. 0:31:06So that's that 800,000 is finishing out the three million dollars.
  238. 0:31:12That the grant will cover 100% of, and then anticipating
  239. 0:31:18change orders or whatever, we are finding that the… the roads are in a lot worse condition.
  240. 0:31:25what we thought they were, so we're going to be doing more paving to put the roads back together, so that's anticipated. So will we amend down, then, or anything?
  241. 0:31:36For the 26, because the money is going to be… No, that… 27? No, that 20, that, that 26 is a good number. That's, that's, that's where we're… Right, the activity, but you're talking the amended budget is still good? Yes.
  242. 0:31:49Yeah, because that's tracking with those spreadsheets that I share with Caitlin and you, and all that stuff, as far as the reimbursement accounts.
  243. 0:31:59So right now, when I make a reimbursement to the EPA, we're getting 100% of that back. Until we hit our 3 million. Until we hit our 3 million. So, for instance, and we're talking to MDOT about it, there was… supposedly there was a water main
  244. 0:32:15on River Road, from East River Road to West River Road, under 23, that was installed back… supposedly installed back in
  245. 0:32:2520… I'm not sure when. So we… we originally had it in our… in our project. We took it out when MDOT said, no, we've got Asbill plans, it's there, and all that stuff. Guess what?
  246. 0:32:35They paid for a water main that never was installed.
  247. 0:32:38So, they are looking into it.
  248. 0:32:41So, but we had… we had to make that connection, so we had to do a bore under 23, so we got some of those miscellaneous, these that are going to creep up? Could… could creep up. We're tracking them closely, so… CHAF is doing a pretty good job as far as keeping our costs in check, so… That's why… so essentially…
  249. 0:33:00Early 2013, 14, somewhere in there.
  250. 0:33:05Was this when they did the road replacement, or… I think so, yeah. M&M was the contractor. It's 2012. And MDOT's inspector drew up as-built plans that showed that it was constructed, so…
  251. 0:33:19So… And it wasn't. We found out, our shop found out it's not safe. So I'm talking to, the TSC manager and that, as far as… they're asking for all of the documentation that we've… Because, like, what's the remedy for that?
  252. 0:33:36That's… that's… that's internal. That's internal to them.
  253. 0:33:41I said that… I said that we're going to be very interested in it, because not having that in our bid, and as a change order, the price was a lot higher than it would have been as part of the bid, so… What's our risk here that it's more than $800,000? Because $750 is the 25%.
  254. 0:33:57So everything… I went… I was conservative in my $800,000 figure, so… Thank you.
  255. 0:34:11Back, back to… just so the 24 DWSRF project is complete, that's why there's nothing there. The C2R2 project is now complete, so that's why there's nothing there for 2027, so…
  256. 0:34:25Okay, Megan.
  257. 0:34:27Semi-reduction or I guess, a request.
  258. 0:34:33I don't know who to direct this to, necessarily, but just for, like, on our chart of accounts, the actual account name, for the change of other… or charges of other services and charges for services sales, is there a reason we can't just get, like… Yeah, I don't see why not. RTS on there.
  259. 0:34:50What would be the other one? I guess the main one just would be charges for other services would just be ready to serve. Okay. For that and sewer. Just a qualifier. Yeah, just… I got it. Just so it's super clear and jumps right out at you. Yeah.
  260. 0:35:03I'm good with that. And sales is an interesting way for us to call that for our service.
  261. 0:35:11Isn't that the actual usage? That's actual usage, yeah. Service fees. That would be the same, yeah. I know. Would you like usage? Doesn't matter. I mean, that's more reflective of…
  262. 0:35:25It is for the normal person to understand what we're talking about here. But ready to serve, I think, is the more important piece, just so everybody knows what that actual line item is.
  263. 0:35:36No.
  264. 0:35:38Yeah, everything else is pretty much,
  265. 0:35:42as it was, the water tap, again, we'll discuss that. I don't see that any different than the sewer. Yeah, it's the same. It's being under… And between the two, the sewer, the sewer side, as far as fees go, the labor is basically what's increased there the most. The water side.
  266. 0:36:02meter pits, meters, the piping and all that stuff has really went through the roof during COVID. Where are you talking about for this? That, 591-000-642-100.
  267. 0:36:16The water tap fees.
  268. 0:36:19We're gonna be… we're gonna be revisiting those as far as maybe increasing those fees, or making a recommendation to increase in another form, which then may adjust this. Gotcha.
  269. 0:36:37Under hydrant rental, the 591-000-667-200, is there a reason why we're not recording the revenue there?
  270. 0:36:47Some… they, like, out at Coletta, they'll meter the usage of water and
  271. 0:36:54We've talked about that. I'm just curious about… Right. Agent rental. They just use the billing for that, too, where they bill it through their system. Oh, I… like, why we're not…
  272. 0:37:022020, 2024, 25, or this year, but I… Is it possible that they bill it to the user? Like, yeah, like, as an example, and I don't know where it's going. They actually sent them a bill, like, they're supposed to be creating their billing system, yeah. Like, it's not one of the ones that I invoice for.
  273. 0:37:26Like, like, Northern Strike, for example. Right. So they use water. Yep. And there were meters on that.
  274. 0:37:36So, I just couldn't figure out where… why it's not… you want it under hydrant rental. We need to have it in there.
  275. 0:37:43I know, I know. I know we invoice it and we collect it, it's just where we put. Right. I don't know if it's water.
  276. 0:37:53Sales. Oh, you don't… They bill it through their systems. There are some smaller ones that, like, but I have to go and see… I'd have to look at the line item. I'm just curious on the closing the loop of all those things. Yeah. You know, how do they know that we've closed those loops? It's things for, like, construction projects, too. Like, sometimes they'll hook up to, like, a metered hydrant, and they have
  277. 0:38:16Like a measuring system. But from what I understand, when Hannah was here, she told me that they switched the billing so that it bills somehow through their system. That there are very few now that, like, I have one on my desk, but it's one in the last year that doesn't apply somewhere else. So, I mean, I would assume it maybe is through their other accounts? I don't know. That's a good question, though.
  278. 0:38:37I mean, the only other place in our budget that, if it's going anywhere, would just be in sales or other service. Right. Those are the only two places you can capture that.
  279. 0:38:47That's a good question. I'll… I'll ask.
  280. 0:38:52Okay, we bring it up tomorrow. Yeah, yep.
  281. 0:38:57I would recommend, if she… if… because the current girl there is pretty new, that, definitely reach out to Hannah and get an explanation of…
  282. 0:39:06that system, because we did have a conversation about it earlier this year, and that was my understanding, was that I would no longer be getting those, like, anything to invoice, pretty much, that they were going to bill it through their system. So instead of me creating an invoice, like, it bills the same way that their little, like, the little cards do. So, which makes it more… I mean, it makes sense to me, it's very consistent. Exactly, and it kind of closes the feedback loop, because right now.
  283. 0:39:31we have a manual closure of the feedback loop when I invoice anything, right? We have to communicate really well, or else we don't always know. Otherwise, yeah. So, whether it's… So…
  284. 0:39:42Just so that I understand this, because… I'm in another world.
  285. 0:39:49You're saying that the people that are using the metered hydrants
  286. 0:39:54Are actually getting a paper bill.
  287. 0:39:58We're saying we're going to investigate this, because that's my understanding, that most of them are getting billed through the water, actual water system. Okay. We need a clarification, so that no one is saying anything definitively at this point. Right, okay. And.
  288. 0:40:12Because… If we have hydrant rental.
  289. 0:40:17Even if they're getting billed that way.
  290. 0:40:20there needs to be a way to see that… that we can show, because too many people have said, Coletta's using all this water.
  291. 0:40:29And nobody's paying for it, so if there's rental.
  292. 0:40:34You know… I've never once heard that, but okay. I'm agreeing with you that we should be tracking it. Yeah.
  293. 0:40:40Yeah, no, I've… I've heard it from A few people.
  294. 0:40:45that they were using township water.
  295. 0:40:48to wash planes and… Things we should probably investigate before we make any type of… Yes, exactly. I can let you know that that is being investigated. Okay.
  296. 0:40:58We have a solution. Yeah, we have a wonderful we have a solution.
  297. 0:41:04It has been looked into, yes. Wonderful.
  298. 0:41:08Any questions?
  299. 0:41:10On the water side. On where? What do you mean, on the water side? We're not even close. Yeah, we already switched to the water. Oh, we're only on the same page. The revenues, I mean, we're switching to… I'm just asking them for some more questions. Not like we're done. On the next page, yes. Okay. What next… what do you got, Mark?
  300. 0:41:29Well, the next page is the busier page. That's what we're all tracking, right?
  301. 0:41:34We start with Social Security. Yeah. Okay. Yep. Supplies.
  302. 0:41:40Yeah, so coming through here, this is more of, like, informational
  303. 0:41:45Purpose for me to take forward… forward out of this meeting, but… for F&B contracted services.
  304. 0:41:55Just that portion of it.
  305. 0:41:58405. Yeah, and you guys can answer this question better for me, but when we're… as far as…
  306. 0:42:06our services from FNB. Is it fair to say that the absolute majority of that is manpower labor? Obviously, there's vehicles and stuff in there that we're not paying directly for, but they have that cost. But their major cost for servicing our contract is…
  307. 0:42:24Manpower.
  308. 0:42:26some equipment.
  309. 0:42:28and chemicals. What am I missing? In their contract, they have a chemical allowance.
  310. 0:42:35For the chemicals they use out at the wastewater treatment plant, which will be being adjusted with the new PFAS treatment and all of that. And but yes, it's mainly labor, the vehicles, and the chemicals. Monitoring.
  311. 0:42:51Yeah, so monitoring, yeah, and so is that cap… is the chemical… are the chemicals captured in
  312. 0:42:56this, or is that a fluctuating number? That's a… it's in their contract. They… what we do is we have a $20,000 chemical allowance in their contract. They track it, they provide us the information on a monthly or quarterly, and then if for some reason they're going to exceed it, they let us know that they're… But that's $20,000 out of $853,000.
  313. 0:43:20that we spend on the only reason I'm asking how many How much staff?
  314. 0:43:24They're here regularly. Including the water billing clerk, they have 6 staff.
  315. 0:43:32dedicated to, Oscoda Charter Township, and that was… Does that include Catherine as the director? As the project manager. And that was… that was a big point of contention with their
  316. 0:43:46contract… their renewal of their contract… I'm listening. …was to… was to make sure that they had
  317. 0:43:536 dedicated staff to the township. We have their names, we have their certifications, we have their contact information, and all of that. Okay.
  318. 0:44:02Because there was some… Thought that, you know, they… they… at any given time, we didn't have 6 staff.
  319. 0:44:11Right. You know, working in… Do you recall, or does anybody recall, what full-time staff we had when we operated our own water department?
  320. 0:44:19Good morning, folks.
  321. 0:44:21Yeah, if we don't have an answer, we don't have to… we don't have to guess at it now.
  322. 0:44:28Probably asked around. No, I'm just… I know we just renewed contract and everything, but, you know, we're… I mean, if we're being honest, across the board, as far as an overall budget, not just individual
  323. 0:44:40funds. I mean, we're… we're facing some challenges here moving forward this year, next year, the following year. So, I don't know. I mean, 6 full-time staff.
  324. 0:44:52It's $142K a person, and the lion's share of the entire expense is the employee
  325. 0:44:59a handful of trucks. The chemicals are minimal, and those fluctuate anyway, so those are charged as is afterwards.
  326. 0:45:05I don't know. I'm not advocating for one thing or another. I'm just… obviously, those are the largest controllable expenses on here, to the extent that you can control them. So I just wanted some information, that's all.
  327. 0:45:16No other questions on this, other than…
  328. 0:45:22Essentially, the engineering fees are just appropriately allocating
  329. 0:45:26our actual real full-time engineering fees, right? We're finally getting them a place where they should have been.
  330. 0:45:37So I'm… I'm good with that. I mean, we should be seeing consistency there moving forward, is really what I'm saying, instead of us jumping around every year.
  331. 0:45:47And as projects reduce, we should be seeing them go down this level. Yep.
  332. 0:45:52This would wrap into more… I'll become more part-time, semi-retired in Sault Ste. Marie. What are you working for? But I'll be employed.
  333. 0:46:06But yeah, so yeah, we're finished two projects. All right. 26, so yes.
  334. 0:46:11She
  335. 0:46:13But there's always going to be projects. Yeah, there's others coming, yeah. Exactly. I would say the next largest one is you flip the page, the offshore utility. 700.
  336. 0:46:27Boom.
  337. 0:46:28$25,000 budgeted.
  338. 0:46:33I know we did just budget for some leak detection, so hopefully that helps with our water loss issues.
  339. 0:46:41With all the, reconstruction on River Road and Lake Street, have we come across anything substantial that has been, okay, this is probably going to be helpful? Out of… For water loss. The last number I had, I have… 40 services that they've come across out of 90.
  340. 0:47:00Over 30 of them were leaking.
  341. 0:47:02Oh, that's all. On River Road?
  342. 0:47:05Just in the downtown, downtown water system, and 3… It's a lot.
  343. 0:47:11That's one third. Yeah, I think there's three hydrants. There was three hydrants that were… Three or two, I don't know.
  344. 0:47:17Pretty significant. Obviously, before meters, so uncaptured. Right. Yeah, yeah, yeah, everything downtown is… the meters are in the buildings for the residents, so yeah.
  345. 0:47:29And, and again, it all goes back to that, is with the sandy soils, there, there's really… we're not going to see it. It goes right out. Yeah, it does. Like here.
  346. 0:47:39Yeah, so… I don't actually see the water level rise, but… Thanks for that update.
  347. 0:47:52capital improvement. Can I point out something before you go down that way?
  348. 0:47:58When we were talking about telephone before on water, it was 20,000. On this page, it's 1,500.
  349. 0:48:06Correction. On sewer, it was 20… Oh, on sewer, it was 20,000. Water is 1,500.
  350. 0:48:13The telephone? 853.000 at the top. Yeah.
  351. 0:48:20I'll look into the discrepancy. Yeah. Why it's 20… I actually have, like, a note here to look at all the utilities.
  352. 0:48:29I'll go… I'll book an appointment with Caitlin, and I'll go through all of these, because we have the electric… we have, like, 70 electric bills that
  353. 0:48:37I don't think anyone has reviewed in any kind of recent history. When Jane was still there, she did her best to go through and, like, figure out, you know, what was supposed to go where, and I'm still using her, like, format, but there's probably been some changes.
  354. 0:48:51So, I'll do that. We've done it with the water bills already, but I will work on everything else, too. Yeah, 18,500 difference is a big thing. I'm researching one from our water main projects.
  355. 0:49:05That was out by the schools.
  356. 0:49:08I think the meter bit that we installed.
  357. 0:49:12that is metering, because we're drawing water from Asabo. Okay. I think we're still paying that utility bill, and that should be converted or switched to Asabo.
  358. 0:49:23For that meter pit. Oh, okay. I'm going… I'm going back and trying to see where that was all at, and to see if it did get changed, or if it needs to get changed. Okay. We have the new telephone, lines that were installed for the sewer system, too, that we just did.
  359. 0:49:42So that's kind of… That's why we would have an increase over that, okay. Yes, that makes… that makes a lot more sense. But I will…
  360. 0:49:54Investigate anyways, make sure that that's what it is, and not something else.
  361. 0:50:01Oh, there was a security brief? Yes, that's right. Okay.
  362. 0:50:06That's what that increases for sewer. Cellular, loading. Yes, exactly. We had to purchase… But really, it should be on water, not sewer. Right. So, maybe it's flopped.
  363. 0:50:24Okay, as we move down, another course of the capital improvement, which is that last page.
  364. 0:50:32Oh.
  365. 0:50:33And the packet explains the 230.
  366. 0:50:38Sorry, there's been no repairs and maintenance activity for 26?
  367. 0:50:46I'm still on the previous…
  368. 0:50:49We have a budget of $20,000 for this year, requested $20,000 for next year, and no activity for this year. I wonder if there's something that's supposed to be going in. Yeah, that hasn't been.
  369. 0:50:59Where you going?
  370. 0:51:01I wonder if that was,
  371. 0:51:04the cars. There would be an… there's a vehicle equipment. Oh, true. Also. Changes. 591901.
  372. 0:51:139, 7, 4.
  373. 0:51:15Thank you, Catherine, for your outlay. That's not what I'm looking at. I'm looking at repairs and maintenance, 5569. 930, 931. No activity. Jump to something else. All right.
  374. 0:51:29The way to investigate these is to go and look back at 24 and 25 and see what went there, and if there is… if there are things that are, like, being charged wrong, we can go back and reclass them 30 years over.
  375. 0:51:41I can look at them right now.
  376. 0:51:50Right. Maybe the capital improvement.
  377. 0:51:55Leak detection monitoring system, 30,000. I think they're waiting. I think they're waiting, because she's looking for something else.
  378. 0:52:08Do you want us to wait while you look that up? No, I don't think so. Oh, all right. I thought that's why you were looking over there.
  379. 0:52:15I didn't… maybe I didn't see the hand signal, because… No, there was one. There was no hand signal. Okay. Sorry, I forgot I was running the meeting. My bad. Hydrant replacement valve outside. Is this.
  380. 0:52:28Outside Portsmouth? Yes, yes, that's what… yes. Okay. Yeah, that's the… that's the one… What we didn't get… what we didn't get quoted in the 2027. Number… what number is that? Capital improvement on that last. So, if you look at the capital improvement, 591-901-974,
  381. 0:52:470, 0, 0.
  382. 0:52:50Should be on that third page, right there, all the way over. There it is. Okay. And then, if you look at the very last page.
  383. 0:52:58the draft capital improvement, it explains what that 230 is. Very good.
  384. 0:53:09Yeah, since we didn't get funded for the 2027… Right.
  385. 0:53:14drinking water, which was going to take care of the rest of our hydrants. We've programmed to take care of a sample of them.
  386. 0:53:22Over the next couple of years.
  387. 0:53:24out of our CIP. Unless we get another. Unless we get another, yeah.
  388. 0:53:31So we don't want to replace them all at once. Yeah.
  389. 0:53:35Just… it just says, Well.
  390. 0:53:42Yeah, the hydrant valve says outside of worksman. Yep, yes. You're just gonna pick whatever the best ones are. The 2024 DWRSO took care of everything on the base.
  391. 0:53:56All of them? Yes. Okay, yeah. So, we… this next one was going to take care of the rest of the township outside of the base that were still deficient. Okay, so we get… we get… we get an inspection each year from EGLE on Bay City, and they give us a list of whether we're doing… whether we're doing good.
  392. 0:54:17not so good in what we need to improve on. Gotcha.
  393. 0:54:20But they're very… their understanding is… or nothing goes.
  394. 0:54:28I'll certainly look at it.
  395. 0:54:32And then, yeah, nothing contribution, bond, interest, expense. Mark, do you have any questions on that one? Same question as the last one, which is, hey, is it because we got…
  396. 0:54:44you know, principal forgiveness early on, and it's coming back. Yeah, on the water side, we did not get as much principal forgiveness as we did on the sewer side, so…
  397. 0:54:53I mean, if that tracks with the schedule, we're good.
  398. 0:54:56That's what I do about that.
  399. 0:54:59The… Well, here's one extra question. The additional contribution from the general fund?
  400. 0:55:08To the general fund. To the general fund.
  401. 0:55:11Okay, thank you. Read that wrong.
  402. 0:55:14The same number as… It's a big difference. Yeah. One direction or the other.
  403. 0:55:24So both of them are contributing back to the general fund.
  404. 0:55:2890,000.
  405. 0:55:30Small amounts, but still positive. Okay, absolutely. That's.
  406. 0:55:35Is that all we have for…
  407. 0:55:38It looks like in 24, under that line item, water meters were purchased and placed under that line item at that time.
  408. 0:55:46One minute.
  409. 0:55:48for Capital for Life.
  410. 0:55:49background
  411. 0:55:51That was, like, the final year that you had going… you had… you guys were going through a… Multi-year replacement of repairs of water meters. Water meter replacement. Yeah, so that… And that would have been repairs and maintenance?
  412. 0:56:04Do a deep dive with Caitlin on that one. Yeah. Because we just processed… she just sent me an invoice, Catherine just sent me an invoice for parts for water meters, and she didn't have any charge in there. So…
  413. 0:56:16I think that was because it was going to CCR2.
  414. 0:56:19Yeah, when I was looking at the supply line, I kept seeing hydrant repair kits.
  415. 0:56:37Should those have gone into the repair and maintenance?
  416. 0:56:40Yeah. And Catherine… I don't know why they're going to supplies. Catherine codes things right now, and so what I'll do is I'll pull all of the invoices out and look at them with Caitlin, and she'll help me reclass anything that needs to be reclassed, and then we'll go forward with Catherine directing where the line item would go.
  417. 0:56:58That's how, I mean, that's what we typically do. This happens more frequently than
  418. 0:57:02Well, less frequently now, but it was really fun in my first year.
  419. 0:57:06Right. Yeah, because you made up a new cheat sheet.
  420. 0:57:10Yes. You're totally… Yes.
  421. 0:57:13Just looking forward on that last sheet you had, the one that you're on right now, just looking forward to Cedar Lake, basically from the intersection F41.
  422. 0:57:23Straight shot all the way to Loud Drive. That one's showing, obviously, our…
  423. 0:57:28next massive project, which one is that? That 2.1 million? Sorry, kind of right in the middle, see, like, road F41? Very last page. He's on the capital improvement. You're not on the… go to the last… very last page. There is no number, that's why, otherwise I wouldn't… sorry. Okay, yeah, that one. Anyway, this is 2028, not 2027.
  424. 0:57:50But just looking…
  425. 0:57:52That's obviously the biggest project we have, even on the… on the books for the next 5 years. Which one is that? Well, that… so it… the water ones that are on this… on that page are the ones that didn't get funded in the 2027
  426. 0:58:08DWR SRF that we just went after. Yep. So we put them… we put them back into here to just keep tracking to… to… so… We still need it. We still need it, and we're researching other funding sources to help us out with that.
  427. 0:58:25But none of these are… absolutely have to…
  428. 0:58:28No, but they are… based on the year, that's when we… That's a priority standpoint. And part of the reason that one, the Cedar Lake Road one, is if ever
  429. 0:58:42the residential development.
  430. 0:58:45Takes off out north of there.
  431. 0:58:47the Lakeshore… the other portion of Lakeshore that hasn't been? Yeah. This is going to be needed for that development.
  432. 0:58:57Increased service line, or… Well, just the condition, no, it's just a… it's just a… we…
  433. 0:59:03Back, if you remember, back a year ago in December, we had that big 12-inch water main break off from this main. It was off of that? Yep. Okay. So, we're monitoring it consistently as far as making sure we got nothing sneaking up on us, but…
  434. 0:59:20So, gotcha. Okay. One, probably water and sewer question related. Our study that we had done for the increases, where are we at on that?
  435. 0:59:32What number, or what year? I believe we still have two more.
  436. 0:59:37year. I just looked at it. And what's the increase? Do we know what percentage of the increase that's… Yeah, it's about 3. Steady 3%. 3 is what… Okay. I'll look back, and I'll come back. There'll be a separate presentation for the Sethos rate.
  437. 0:59:52Right. Yeah, and I'll include that study. Yeah. When…
  438. 0:59:58Jamie, I think you might have missed what Rick said about the new project that includes another rate study for future use, I believe. Every time we do a DWSRF or CWSRF,
  439. 1:00:12They evaluate our rates, and make sure that what we have currently and are programmed covers our
  440. 1:00:21Current debt, and then also future debt.
  441. 1:00:24Okay. With, you know, so… and I think last year, when we talked about it, I think, you know, I mean, I'm not saying that there won't be an increase, but I think we're in probably pretty good shape still. Okay. Well, I'd like to take a little break if we could. Because… because we have paid off some of those other loans.
  442. 1:00:43Good question.
  443. 1:00:45Madam Chair, it's all… Anybody have any other questions related.
  444. 1:00:51Admin.
  445. 1:00:52The only other question, this… we have the general fund that's left, correct, to do? And a catch-up, and that is scheduled on the 28th, if we want to set another one.
  446. 1:01:04I could certainly bring that to the board on Monday, if you'd like to.
  447. 1:01:10another one after that one, just to make sure we get everything in. Does the 28th include the general fund and catch-all at the same time? Yes. Usually, I mean, we can separate out… I think… I don't remember how it was originally written, but I believe it was…
  448. 1:01:27General fund plus all the other ones we hadn't touched.
  449. 1:01:31And then… We can schedule another one, too.
  450. 1:01:35Typically, I think we would get a draft budget after that one, and then, the public hearing would need to be scheduled, and that's tricky because it's around the holidays, and it has to have at least a certain amount of notice. I definitely think that that should go into work. In the last two years, that's only the experience that I have.
  451. 1:01:53We've done the public hearing at our first regularly scheduled board meeting, and then we needed to schedule a special meeting, but you can do the public hearing and also pass the budget on… at the same time. So the second meeting has only been because
  452. 1:02:08We did not have enough information, or the board felt like they wanted another work session. So both years, we did the public hearing, had questions, tabled it.
  453. 1:02:17held a work session mid-December, and then held that special meeting the second Monday of December.
  454. 1:02:23So
  455. 1:02:25I'm not saying that that is the timeline I'm married to. I actually would prefer it to be a little more…
  456. 1:02:30a little sooner, you know, do it as intended, but to do it sooner than later. So.
  457. 1:02:38So, on the 28th, We have the last one. Do we want to schedule another one after that?
  458. 1:02:46Talked about it.
  459. 1:02:48Bless you on Monday, or
  460. 1:02:50I mean, certainly we can bring it up. Yeah, I'd say that's the topic to talk about, anyway. Isn't it always better to schedule one and then cancel it, versus having to schedule one after?
  461. 1:03:03Yeah.
  462. 1:03:06Okay, I'll put on the agenda to schedule one more budget session after the 20th.
  463. 1:03:11the 1st week or 2 of November. Yeah, I'd look for it. We'd be fine.
  464. 1:03:16What are we calling that, though? Are we calling that draft review?
  465. 1:03:21Like, will we have a draft to be able to review? My question, too, is that if we… if we have our next work session, and then, like, the next step would be a draft budget, so if we don't have a draft budget prepared that fast, like, if the week is not long enough from the 28th to the next Wednesday, then it should bump to the next one.
  466. 1:03:38I'm… So you want.
  467. 1:03:41one more work session, then a draft. And that would be, like, we would go through, and anything we had questions on at prior work sessions, we would double check that those got corrected, any final thoughts that come up.
  468. 1:03:53And if that goes well, and there's nothing major, then the public hearing could be scheduled, and the budget could be put up for, yeah, for board consideration at the first December meeting, which is also probably when fourth quarter budget amendments should be presented as well.
  469. 1:04:16Is 2 weeks enough time after we do the general fund?
  470. 1:04:22catch-all session to be able to set up a draft budget review, so that would put up almost… Well, I don't see why not. We're just plugging in the numbers that you all have suggested, and I've been plugging them in as we've been having these sessions, whatever changes.
  471. 1:04:40I actually… And probably more concerned than Clerk T on timeline.
  472. 1:04:47just… I mean, the last couple years running into end of December.
  473. 1:04:54This question will begin with this year. We have lots of changes. We have Multiple changes in board seats.
  474. 1:05:03You know what I mean? We, we have.
  475. 1:05:06contract… contract negotiations. We have… maternity leave possibilities, all those things all happening between now and December.
  476. 1:05:16So… I don't see… I mean, we'll do the 128th.
  477. 1:05:21And, we can schedule a draft review.
  478. 1:05:27On the 4th? Yeah, I don't know, that's only one week. It's also election week, and I'm not coming until you're that day, I'm sorry. Exactly. No, I understand that. The day before, I limit, so…
  479. 1:05:39So.
  480. 1:05:41November 11th? Maybe, I think. Veterans Day? We're closed on Veterans Day. Okay, so the 12th? 12th? It doesn't have to be…
  481. 1:05:51Specifically on the 12th. Thursdays are always… Or the 10th. Bad for me. What about the 10th?
  482. 1:05:5710th is better. I think also the notice would have to go, because our board meeting in December, if we're aiming to do public hearing past the budget at our first regular meeting in December, our only regular meeting in December, the notice has to go in on December 2nd, the paper on December 2nd.
  483. 1:06:13Which means that the deadline for the newspaper is Thanksgiving weekend, which is likely that they will tell you it's an earlier deadline because of the holidays. Right.
  484. 1:06:21just, like, this is what… this is what we ran into last year, too, is that, like, once you get past October… Well, we can always schedule the, the public hearing.
  485. 1:06:32Right, the note… I'm talking about the notice, though, specifically the newspaper deadline for the notice. Speaker 3 : It has to be in the paper for at least 10 days, which means it has to go in, like, almost 2 weeks before our meeting, so what I… and I'm not saying you guys have to do it this way, what I did last year is I took a map, like, I mapped out the dates of everything and the hard deadlines, and then I bumped soft deadlines into, so that when, you know, we… if we didn't have a quorum, if there's a snowstorm
  486. 1:06:57or something on the day that we have the meeting, then we have some… we had a buffer, so it wasn't… I didn't feel like we were trying to…
  487. 1:07:04come in at the last minute. Well, hopefully we have people appointed to seats and everything else. I'll, do that.
  488. 1:07:10I'll be really honest, 14th, right?
  489. 1:07:15maybe I'm ignorant to what's going on at Township Hall right now, but I'd actually be in… like, I'd have… my preference would be the 1028 meeting actually be draft budget review.
  490. 1:07:27and have our general fund review sometime in the next 3 weeks. Like, the 21st? Prior… prior to that. I know Mr. Klein has a vacation in between there. Right.
  491. 1:07:38So I don't know if that's possible or not. Maybe it's not, but…
  492. 1:07:43I mean, our next review's not even for another 3 weeks, and that's for the general review catch-all meeting. Yeah, I think that… And then we fight holidays after that. We've got a lot going on. Well, I don't… Certainly, we… certainly.
  493. 1:07:55schedule it, I mean, I just won't be here. At our board meeting, we could schedule the, I won't be here, they're on the 14th, but you guys could do it on the 14th.
  494. 1:08:04like, basically move what we're supposed to do on the 28th up a little bit, so do general fund catch-all on the 14th or the 21st. The only problem is with…
  495. 1:08:13Who's not available on the 21st? Winter vacation. I forgot. You know, my business.
  496. 1:08:23Bye!
  497. 1:08:24The 14th, are you back on the 21st? Okay. Through the 23rd. Okay. So, I'm gone the week of the 13th, 13th, like, after 18th.
  498. 1:08:37Yep. So that's why we didn't put it those two weeks, is because people were gone.
  499. 1:08:43That's fine. I mean, we can… we can leave as is, it's just a… This point is already better than last year, and way better than the year before, so I understand what you're saying, Mark, and I do agree.
  500. 1:08:53as I, you know, have said, but… Just to say we're due for a lot of special meetings. Yeah, I mean, it seemed like December is special meeting season, I guess. That's when Adam is coming also? Adam's on the 14th or the 23rd. The challenge is you'll have multiple board members that are…
  501. 1:09:13New, or haven't attended these meetings, that will have to be… That's what having additional discussion.
  502. 1:09:21And requesting changes. Then we ended up having special meetings. Which is what happened last year. We had special meetings.
  503. 1:09:28I just… I'm trying to avoid that, but it doesn't sound like we can, so… Okay.
  504. 1:09:38Okay, any other thoughts? Change the fiscal year, or… Oh, just, Go with it.
  505. 1:09:48The only other thing I'm going to ask for is if we could please get the information for the draft of the General Elector one out at least the day before. That would be greatly appreciated. There's a lot to cover.
  506. 1:10:03I really like the format that you guys chose for this logo. I think this is a winner.
  507. 1:10:08to read, it's really well done. Yes. I like that it has the topics at the top, but you can just print that right out of ESNA, you don't even have to mess with the… Oh, yeah, I will tell you, it's because these are separate funds, it is extremely easier, and you don't have to…
  508. 1:10:24We did these last year, so I know exactly what you're saying, but it's possible to do it with all of them. You know the trouble that Karen went through. Yeah, that's why I'm acknowledging it now.
  509. 1:10:36Any other thoughts?
  510. 1:10:38I'm going to join this workshop at 7.12pm. Thank you, Rick, and Adam and Karen, for your work.
  511. 1:10:45And everyone else for attending. Thank you. Sorry.